Mei 24, 2021

2020

A successful year during the COVID-19 Pandemic, achieving the dual objectives of (a) maintaining the health and safety of our personnel, and (b) to continue operating […]
Mei 24, 2021

2019

Another record-breaking year for ore processing, AGINCOURT RESOURCESmilled 6.0 Mt of ore to produce 391,031 ounces of gold, while maintaining low All In Sustaining Cost US$443/oz.We […]
Maret 29, 2019

2018

Production results again exceed key records set in preceding years. A record 5.57 Mt of ore is processed to produce 410,387 ounces of gold, a 15% […]
Maret 29, 2019

2017

Mining commences at the Ramba Joring Pit. The end of 2017 sees the most successful production and exploration results in AGINCOURT RESOURCES’s history. The operation milled […]
Maret 29, 2019

2016

Following successful completion and submission of appropriate documentation, approval for mining at Barani and Ramba Joring pits is issued by the Indonesian Government in March 2016. […]
Maret 29, 2019

2012

Completion of project construction is followed by plant commissioning and commencement of operations. Commissioning approval for mine discharge is received from the Tapanuli Regency. The first […]
Maret 29, 2019

2011

Construction activity reaches a peak with more than 4,000 workers at the site, 40% of whom were recruited locally. Construction of the Tailing Storage Facility is […]
Maret 29, 2019

2009

  G-Resources, a Hong Kong publiclylisted company, takes over ownership and development of the Martabe Gold Mine Project in July 2009.
Maret 29, 2019

2008

Twenty-five environmental studies completed for the project. Key documents and government approvals are obtained, including a Feasibility Study, Environmental Impact Assessment and a construction permit. Construction […]